Breaking ground on the next chapter of the AutoMotorPlex! Initial site clearing, excavation, and earthwork mark the beginning of the Phase 3 expansion in Medina, MN.
The next major milestone is underway as crews begin grading and shaping the Phase 3 property, establishing the foundation for future infrastructure, roadways, and new garage condominium buildings.
Crews begin installation of underground utilities and essential infrastructure, including water, sewer, and electrical services. This critical phase of construction prepares the site for future building development and brings the Phase 3 expansion one step closer to reality.
All underground utility installations are complete, with required testing and inspections successfully performed. This milestone marks another major step forward in Phase 3, bringing the development one step closer to construction, starting with Building One.
The final expansion at Medina is underway — this is the last chance to be part of the community. Have questions, or just want to know more?
Contact: sales@automotorplex.com